| Gross Head | : | 230 m |
| Net Head | : | 217.80 m |
| Turbine | : | Two units of 4.5 MW capacity |
| Generator | : | Two 5.1 MVA capacity generators will generate electricity at 6.3 KV voltage level. |
| Transformer | : | Two 6 MVA capacity three-phase transformers will be installed and the generated electricity at 6.2 KV voltage level will be stepped up to 33 KV voltage level for transmission. |
| Transmission Line | : | A transmission line of about 15 km length will be constructed from the project’s switchyard to the connection point and will be connected to the Nepal Electricity Authority’s Kirtipur substation. |
| Connection Point | : | It will be connected to the 132 KV busbar of NEA’s Kirtipur substation. (The electricity to be connected in Kirtipur will be transmitted through the Udaipur 220/132 KV substation under the NEA’s Manai-Bharatpur 220 KV transmission line.) |
| Annual gross contracted Energy | : | 51,570,686 unit |
| Dry Season Energy | : | 15,958,851 unit(mangsir 16 – jestha 15) |
| Wet Season Energy | : | 36,611,835 unit(jestha 15- mangsir 15) |